=== Purpose === | === Purpose === | ||
To display all circuit Re-ratings in the Forecast or Powerflow Case Definition individually. | To display all circuit Re-ratings in the Forecast or Powerflow Case Definition individually. | ||
+ | |||
+ | === Items === | ||
+ | {|class="wikitable" | ||
+ | ! Data Item !! Description | ||
+ | |- | ||
+ | | | ||
+ | :''Name'' | ||
+ | | | ||
+ | :Identifies a Group Constraint used in the Definition. (Typically the same names as used by the System Operator.) | ||
+ | |- | ||
+ | | | ||
+ | :''Date From'' | ||
+ | | | ||
+ | :Date on which Constraint becomes effective | ||
+ | |- | ||
+ | | | ||
+ | :''TP From'' | ||
+ | | | ||
+ | :Trading Period in which Constraint becomes effective | ||
+ | |- | ||
+ | | | ||
+ | :''Date To'' | ||
+ | | | ||
+ | :Date on which Constraint ceases to be effective | ||
+ | |- | ||
+ | | | ||
+ | :''TP To'' | ||
+ | | | ||
+ | :Trading Period in which Constraint ceases to be effective | ||
+ | |- | ||
+ | | | ||
+ | :''Equation'' | ||
+ | | | ||
+ | :The Formula to be applied in working out the Constraint value for any given Trading Period (typically a matter of summing the products of powerflow and a load sharing distribution factor for each circuit in the Group) | ||
+ | |- | ||
+ | | | ||
+ | :''Limit'' | ||
+ | | | ||
+ | :The maximum permitted Value before the Constraint becomes binding | ||
+ | |} | ||
+ | |||
+ | |||
+ | NOTE: The values of all fields in the Grid can be edited except for the Group Constraint Name which can only be changed using the '''''Edit Equation Constraint Window.''''' | ||
+ | |||
+ | |||
+ | === Usage === | ||
+ | <span style="color:#2E5894"> | ||
+ | '''>> Double click a row to open the associated '''''Edit Equation Constraint Window''''', where Constraint details can be edited. | ||
+ | |||
+ | <span style="color:#2E5894"> | ||
+ | '''>> To add a new Group Constraint to the Schedule:''' | ||
+ | #Select a row containing the name of the Group Constraint to be entered and press the <INSERT> key | ||
+ | #This opens the '''''Activate Equation Constraint Window''''' with the "current" Equation Constraint selected | ||
+ | |||
+ | NOTE: The Equation Constraint Dialogue lists only those named Equation Constraints that have been loaded into the Forecast Definition | ||
+ | |||
+ | <span style="color:#2E5894"> | ||
+ | '''>> To Edit details of an existing Group Constraint in the Schedule:''' | ||
+ | #Highlight the Grid Cell you wish to alter (you can alter all fields except for the Equation Constraint Name) | ||
+ | #Type the new value in the Cell, or press ''<F2>'' to edit the current contents | ||
+ | |||
+ | <span style="color:#2E5894"> | ||
+ | '''>> To Delete an existing Group Constraint from the Schedule:''' | ||
+ | #Press the ''<Delete>'' key. You will be asked to confirm the deletion before it takes place. | ||
+ | |||
+ | NOTE: The Equation Constraints Schedule Grid can be sorted by any column by double-clicking on the column header. | ||
+ | |||
+ | |||
+ | '''WARNING!''' It is possible to create overlapping Group Constraints using the Equation Constraint Schedule. ''EMarketOffer'' sorts the Group Constraints by start and end dates and applies each one sequentially. This means that for any one period the last Constraint applied will be effective in the dispatch calculation. To see the actual order in which Group Constraints will be applied refer to the '''''Edit Equation Constraint Window.''''' | ||
+ | |||
+ | |||
+ | === The Activate Equation Constraint(s) Window === | ||
+ | |||
+ | ==== Purpose ==== | ||
+ | To activate one or more Group Constraints in a Forecast or Powerflow Case Definition. | ||
+ | |||
+ | ==== Features ==== | ||
+ | {|class="wikitable" | ||
+ | ! Feature !! Purpose | ||
+ | |- | ||
+ | | | ||
+ | : |
Revision as of 11:39, 25 January 2013
Purpose
To display all circuit Re-ratings in the Forecast or Powerflow Case Definition individually.
Items
Data Item | Description |
---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NOTE: The values of all fields in the Grid can be edited except for the Group Constraint Name which can only be changed using the Edit Equation Constraint Window.
Usage
>> Double click a row to open the associated Edit Equation Constraint Window, where Constraint details can be edited.
>> To add a new Group Constraint to the Schedule:
- Select a row containing the name of the Group Constraint to be entered and press the <INSERT> key
- This opens the Activate Equation Constraint Window with the "current" Equation Constraint selected
NOTE: The Equation Constraint Dialogue lists only those named Equation Constraints that have been loaded into the Forecast Definition
>> To Edit details of an existing Group Constraint in the Schedule:
- Highlight the Grid Cell you wish to alter (you can alter all fields except for the Equation Constraint Name)
- Type the new value in the Cell, or press <F2> to edit the current contents
>> To Delete an existing Group Constraint from the Schedule:
- Press the <Delete> key. You will be asked to confirm the deletion before it takes place.
NOTE: The Equation Constraints Schedule Grid can be sorted by any column by double-clicking on the column header.
WARNING! It is possible to create overlapping Group Constraints using the Equation Constraint Schedule. EMarketOffer sorts the Group Constraints by start and end dates and applies each one sequentially. This means that for any one period the last Constraint applied will be effective in the dispatch calculation. To see the actual order in which Group Constraints will be applied refer to the Edit Equation Constraint Window.
The Activate Equation Constraint(s) Window
Purpose
To activate one or more Group Constraints in a Forecast or Powerflow Case Definition.
Features
Feature | Purpose |
---|---|
|